Bill of Material. MRP, Production Management, Product Configuration
Recently active
say bomA using RM A in op10, last cost for A is 6.0010 days later, new po cost for A is 7.00.how can i update bomA to reflect RM A to 7?thank youZoey
Good morning, i am trying to create an estimate for an inventory( finished good) from BOM,estimate has been enable, but when i tried to use copy from, this feature is grey out. Please help. thank youZoey
GOOD Morning, our current inventory id, some of them are long: more than 10 characters.. it looks like Acumatica can only accept 10. is there a way we can set it up to meet our need when go live?Thank youZoey
Labor A clock entry into a work order 1, when I try to test if A can clock in to run Work order 2 at the same time, looks like A has to clock out from Work order 1 first.. but the real situation is A can work on 1 and 2 at the same time.Does anyone know how to solve this problem?thank youZoey
We are trying to set up the Mobile App for all users to utilize (specifically for Scanning and item lookup). Within our UAT tenant, I have access to all the needed modules within the app, however when I switch over to our main tenant I no longer have these screens. From as far as we can tell, my security settings our the same between the two tenants. Any suggestions on what needs to be adjusted? I’ve attached screenshots of my visibility on both UAT and live. I have double checked that there are no hidden modules in the top left.
When a stock item is redesigned and the original item is still usable, I need a feature to use up and replace the original item. In SAP this is called discontinuation data. In Acumatica, I have no process or control over using up and replacing items. Follow-Up Material: Number of the material that the system uses in materials planning to replace the material to be discontinued once its warehouse stock is depleted. In the material master record and also in the bill of material (BOM), you can define a follow-up material for a material to be discontinued. The follow-up material defined in the BOM has a higher priority than that in the material master record. https://blogs.sap.com/2014/03/12/concept-of-discontinuation-data-material-master-and-bom/
manufacturing environment: there are plenty of reasons to correct a released labor ticket. I read the instruction but i just can’t figure it out.below is an example:the end time is 4:24pm below, say employee 1668 actual end time is 4:20pm. please help how to correct this? - Zoey
Hello, tried many different things to get the Tool Schedule (AM000014) running! Unfortunatelly without any success. Always getting a empty screen. Does someone knows any tip or trick to get some results in that screen? Pretty sure to have all neccessary setup done. Thanks a lot. BR
Hi i am receiving from an po and got this error:it looks like ‘SPLIT” in the location of the warehouse..i did some research and just can;t find the solution for it. image 1 is the error messageimage 2 shows all the location of this particular receiving warehousethe image 3 is the poThank you So much! Zoey
Hello, i set up an OVHD ID, “payroll” type as variable by labor cost.. factor =”1” and my labor cost per hour is $15 in BOM.on the testing production ticket: 2 labor trans.. one last for 1 hour labor cost =$15 ( correct) , but “payroll” ovhd = $4.5 ( expected $15) 2nd labor last for around 1 min.. and labor cost = $.25 ( correct) , but “payroll” ovhd cost =$.08(expected $.25) can someone shed some light please?thank youZoey
Hi has anyone have any experience with setting up floor kiosk for labor hours input by shop floor employees, as well as keying ingood and bad qty from a work order for each operation?thank youZoey
Hi, I´m new in Acumatica and I’ve trying to safe a PO and every single time i got the error message of¨Error: Inserting ‘Production Item' record raised at least one error. Please review the errors. Error: 'Entered Period' cannot be empty. ¨I’ve traced the problem and I get a problem whit the AMProdItem, and really don´t know how to fix it
I am having to adjust prices for vendors periodically, and was wondering if there was a way to do multiple items at one time?
Hi, I use estimates for Manufacturing. when I create a Sales order Quote I link my estimate to the quote. When I copy order to SO it doesn’t carry over my detail line in the SO type. I can see the total amount is correct but no detail line. I need to mark item for production in the SO line. can someone please help me. Thanks
Hello Everyone,We have a requirement where we are using Manufacturing module and trying to map options from "Configuration Entry" pop-up through code but while doing getting unexpected errors like: “Move Next” etc.Sharing our requirement and sample code for your review and feedback, please find details below:Requirement:Created a Configuration ID on Configuration Maintenance screenUsed that record on Sales Order screen under Details tab. Now on Sales Order Save action based on some custom condition we want to check include checkbox, then execute save action on pop-up and then execute FINISH button, available on pop-up. As per below screenshot we want to mark Included checkbox true under OPTION tab for each feature: Pattern, Grove, Doors, Jamb through code. Sample Code:public class KNBCSOOrderEntryExt : PXGraphExtension<SOOrderEntry> { public static bool IsActive() { return true; } #region Persist Override public delegate void PersistDelegate(); [PXO
Have someone ever done an import scenario with routing already hard-coded/inserted into the import mapping? The spreadsheet as data source only contains finished items and components. What I try to achieve here is having a workaround to assign a routing (that has set of standard operations) into a bill. My issue particularly is with multiple operation numbers that need to be inserted. I can only insert one operation with my scenario.Ex:The spreadsheet has data FG1 (finished item) needs Comp1 and Comp2 (material) - split into 2 lines in the spreadsheet. When imported: the BOM will have operation 10, 20, 30 (already inserted in the import mapping)and the above component are placed under operation 10.
I think to achieve that I should join DAC AMConfigResultsOption and AMProdMatl but I have no clue how to do so? Any assistance would be appreciated.
I have a client using the product configurator and they want to roll up pricing based on the parent item and all the selected children options. This client uses discount pricing and the pricing of the fully configured item is subject to a discount which varies by customer. My client would like the pricing to rollup in the configurator such that the base item is discounted but the children are not. The issue is that the calculated price of parent item and the options essentially take on a new identity resulting in a discount on parent and children. Has anyone run into this issue before and how did you resolve it?
I am working with the product configurator and I’ve come across a situation:1. Create a sales orders with a configurated item.2. Configure the item, and push to production to get it on the schedule.3. The configuration changes AFTER the SO is created but before production happens. 4. Delete the production order since the BOM has changed.What we are running into is that we cannot reconfigure the item on the SO, we have to completely delete the SO line and re-enter it to be able to do a new configuration. We are also finding if we configure, but don't push to production, and the configuration changes they cannot pick up the new configuration and reconfigure. Has anyone run into anything similar and are there creative process solutions around this?
Anyone in community using BOM’s with Phantom Items?How does it work for you? What settings work best in your manufacturing facility?We have multiple items with BOM’s with component parts and subassemblies and we want these component parts and subassemblies to have their own BOM. However, we don’t want to have to MOVE all the component part and subassembly Work Orders in order to process the Parent Item Work Order.If Phantom Items will work, what is the best way to set these items up?
how to regenerate MRP by restriction group?
Dear all,I have desperately tried to set up the product configurator for several hours by now. I followed the guidelines by acumatica help portal. However, if I want to try out my configuration with the action test configuration an error occurs “AM Error: The following error message occurred during calculation of a sales price for the EMS-57-EL item: Object reference not set to an instance of an object.”The item EMS-57-EL has a price set in its master data...and it is also referenced to a BOM…Can anyone help me? :(
Hello, Could you help me with the following issues?Where I can found in Acumatica the costs per LOT [broken down into direct costs (RM consumption, power suppy, wages, water + sewage, variable cost) other direct (depreciation), G&A (ammortisation, salary), commercial] ? Is it possible to do the following in Acumatica: Take all energy costs that are assigned to production (e.g. 80% of invoice electricity Q1) and distribute them equally to all articles produced in the relevant period, weighted according to the production quantity of the articles ?Thank you in advance.
Dear all,We have a requirement after MRP calculation which is to allocate by vendor ratioExample:MRP Requirement = 100Vendor A Ratio = 25%Vendor B Ratio = 35%Vendor C Ratio = 55%MRP Allocation:Material for Vendor A = 25Material for Vendor B = 35Material for Vendor C = 55How can we perform like above example? Is there any function in Acumatica can do like that?Thank you for your kind attention.Best Regards,Agung
Does anyone know if there is any progress toward the Vendor Shipments (AM310000) working with the carrier plugins? If not, how do other companies, or what is the Acumatica recommended way, to create an actual, physical shipment after using the Vendor Shipment screen? Many companies send all of their shipments to the shipping department. Ideally, the Vendor Shipment screen would just work with the carriers like the Shipment screen, which is closely resembles. Almost as good would be a ‘Create Shipment’ action which would create an actual Shipment from the Vendor Shipment. Any ideas or suggestions? This must be a common issue for anyone using carrier plugins and needs the functionality of vendor shipments. Thanks!