When running MRP for a finished good marked as MRP item, do I need to mark raw materials as an MRP item also or will the system automatically pull them in?

The idea is to only set the safety stock at the finished good level and run MRP off of that. We want to minimize raw materials at is food production.

 

Thank you.

@michael73 - You need to mark the raw materials as MRP items also. 