MRP Item clarification

  • 10 February 2022
  • 2 replies
  • 51 views

Userlevel 3
Badge

When running MRP for a finished good marked as MRP item, do I need to mark raw materials as an MRP item also or will the system automatically pull them in?

The idea is to only set the safety stock at the finished good level and run MRP off of that. We want to minimize raw materials at is food production.

 

Thank you.

icon

Best answer by Debbie Baldwin 10 February 2022, 16:44

View original

2 replies

Userlevel 7
Badge +2

@michael73 - You need to mark the raw materials as MRP items also. 

Userlevel 3
Badge

Phew! That’s what I did.

 

Thanks Debbie!

Reply


About Acumatica ERP system
Acumatica Cloud ERP provides the best business management solution for transforming your company to thrive in the new digital economy. Built on a future-proof platform with open architecture for rapid integrations, scalability, and ease of use, Acumatica delivers unparalleled value to small and midmarket organizations. Connected Business. Delivered.