MRP Basic Setup


I am attempting to create a flow of basic steps for enabling the MRP feature. Please let me know if I am missing anything in particular, or confirm that the basic steps are included below. Thank you!

 

MRP Configuration Prerequisites

  1. Numbering Sequences: CS201010
  2. Production Order Types: AM201100
  3. Work Calendar:  CS209000
  4. Replenishment Classes: IN208800
  5. Warehouses: IN204000
    1. Review Manufacturing and Location Table tabs
  6. Stock Items:  IN202500:
    1. Review Replenishment Info

 

Configuration Steps:

 

  1. Creating an MPS Type: AM203000
  2. General MRP Settings: AM100000
  3. MRP Buckets: AM201200

 

Step required to view data: Regenerate MRP

Best answer by angierowley75

There is an Implementation Checklist topic for MRP in the Acumatica on-line help file.  I would recommend you cross check your list with the help.

 

View original
Did this topic help you find an answer to your question?

3 replies

angierowley75
Acumatica Moderator
Forum|alt.badge.img+3
  • Acumatica Moderator
  • 775 replies
  • Answer
  • July 22, 2021

There is an Implementation Checklist topic for MRP in the Acumatica on-line help file.  I would recommend you cross check your list with the help.

 


  • Author
  • Freshman I
  • 2 replies
  • July 22, 2021

Great! Thank you!


jeremyd45
Pro I
Forum|alt.badge.img+1
  • Pro I
  • 210 replies
  • December 22, 2021

It would be nice if this actually included all of the details. The help is missing a lot of information. 


Reply