Visual Planing Board- Changing dates and values manually


I want to schedule the day and hour in Planning Board of Mnaufacturing Order manually! This is posible. But here comes the problem:

Each time after saving the new scheduled date the System is reset the date and time on original values? (System is not keeping the manually changed dates!)

I am using Acumatica 2021R2 (21.209.0034)

 

Does anybody have some idea what could be wrong?

 

Thanks a lot!

 

Best answer by Debbie Baldwin

@TimWehrle32 once we enhance the linking of production orders, we plan to support drag and drop functionality in the core ERP. It will take a few more releases but we will get there. 

View original
Did this topic help you find an answer to your question?

7 replies

Debbie Baldwin
Acumatica Moderator
Forum|alt.badge.img+2
  • Acumatica Product Manager
  • 466 replies
  • July 7, 2022

@TimWehrle32 the popup is not supported yet by Development. If you want to change a date for a Production order, you need to set the date on the grid (left) and firm the schedule. 


  • Author
  • Freshman II
  • 9 replies
  • July 8, 2022

Thanks a lot Debbie! Is it also posibel to change the times (Hours, minutes)?


Debbie Baldwin
Acumatica Moderator
Forum|alt.badge.img+2
  • Acumatica Product Manager
  • 466 replies
  • July 8, 2022

@TimWehrle32 - no - we don’t support drag and drop on the board (which is essentially the same thing you are asking for but “manually”) - In later versions this popup is locked down and you can’t get to it so as not to confuse users. We need to do more work on the linking of child production orders before we can tackle the drag and drop functionality. 


  • Author
  • Freshman II
  • 9 replies
  • July 8, 2022

OK. I totally agree!! “Drag& Drop” means at the end to speak about a full APS Solution which is than no more core ERP :-).

 

Thanks a lot for you fast reply!

 

BR


Debbie Baldwin
Acumatica Moderator
Forum|alt.badge.img+2
  • Acumatica Product Manager
  • 466 replies
  • Answer
  • July 8, 2022

@TimWehrle32 once we enhance the linking of production orders, we plan to support drag and drop functionality in the core ERP. It will take a few more releases but we will get there. 


  • Freshman I
  • 16 replies
  • August 1, 2024
Debbie Baldwin wrote:

@TimWehrle32 once we enhance the linking of production orders, we plan to support drag and drop functionality in the core ERP. It will take a few more releases but we will get there. 

Hi @Debbie Baldwin I have a prospect who are looking for the drag and drop capability. I can see on the post below that it looks like the parent child relationship may be in 2024R2.  Do you know if drag and drop may follow ? I know there is now the eWorkplace Apps integration to Siemens Opcenter as well as Lynq, but these both have a significant impact on a prospect’s budget. Having a built in drag and drop production board for simpler manufacturing environments would be handy. Thanks

 


Debbie Baldwin
Acumatica Moderator
Forum|alt.badge.img+2
  • Acumatica Product Manager
  • 466 replies
  • August 1, 2024

@gavinbell68 - yes it is on the roadmap and getting closer now that we have the advanced linking. I don’t have a firm date. 