I can only see Date to set when doing scheduling either forward or backward or manual. 

What’s the workaround if we want to schedule down to time of the day?

Example: need to schedule production order completed by 15-Apr-2024 at 1pm. 

The reason is to allow for despatch process on that day.

Best answer by Debbie Baldwin

@kristianharianja - today we only schedule down to the day. If it is a handful of orders where you need this to happen - you could increase the priority so that they get scheduled first during that day. That’s my only suggestion. Perhaps others may have a better suggestion. 

1 reply

Debbie Baldwin
Acumatica Moderator
Forum|alt.badge.img+2
  • Acumatica Product Manager
  • Answer
  • April 29, 2024

@kristianharianja - today we only schedule down to the day. If it is a handful of orders where you need this to happen - you could increase the priority so that they get scheduled first during that day. That’s my only suggestion. Perhaps others may have a better suggestion.