Hi Acumatica,

I created an Item for a Produce.

There are multiple transactions and changes in Current Cost.

Upon running the Cost Roll. There is a value in Pending Standard Cost

and click Update Pending. On the Stock Items Screen, the Pending Cost Updated

and Update Standard Cost

and the Current Cost is now Updated.

May I ask where 1,063 came from?

Thank you!

Best answer by PragatiMalviya64

​@Fie $1063 is the sum of the cost components (materials, Labor, overhead etc) of the BOM associated with the Finished goods.

View original

4 replies

Forum|alt.badge.img+2

​@Fie $1063 is the sum of the cost components (materials, Labor, overhead etc) of the BOM associated with the Finished goods.

Translate

angierowley75
Acumatica Moderator
Forum|alt.badge.img+3
  • Acumatica Moderator
  • Jun 16, 2025 10:21 AM UTC

Do you have more than one warehouse for the stock item?

This might be best to send through Acumatica support so they can look at the data at each step and provide more specific guidance.

Translate

Forum|alt.badge.img
  • Author
  • Jun 17, 2025 5:51 AM UTC

Hi Angierowley,

I’m using one warehouse for stock items.

Thank you!

Translate

Forum|alt.badge.img
  • Author
  • Jun 24, 2025 1:46 AM UTC

Hi Acumatica Community,

Can you help me figure out where 1,063 is computed?

Attaching the Excel file for the computation.

Thank you!