Multiple Day Run Times

  • 19 September 2023
  • 2 replies
  • 49 views

Userlevel 2
Badge

We have a customer that builds large assemblies.  The welding of these assemblies spans several days.  Since the Bill of Material/Production Order Details only allow up to 23:59 for Run Time, we are entering fractional Run Units to plan hours >= 24:00 per operation. 

For example, if the planned hours are 250 hrs for a weld operation, we would enter 0.04 Run Units at 10:00 Run Time.

However, there are some cases however where we cannot plan the hours accurately due to run units only being 2 decimal precision.  Has anyone else run into this and have another solution?

Thanks!

LF

icon

Best answer by andrestamour43 19 September 2023, 19:35

View original

2 replies

Userlevel 5
Badge +1

@lukef55

Have you considered changing the operation time format on BOM Preferences (AM100000) to a different formant? 

 

Userlevel 2
Badge

That is exactly what we needed @andrestamour43.  Thank you!

Reply


About Acumatica ERP system
Acumatica Cloud ERP provides the best business management solution for transforming your company to thrive in the new digital economy. Built on a future-proof platform with open architecture for rapid integrations, scalability, and ease of use, Acumatica delivers unparalleled value to small and midmarket organizations. Connected Business. Delivered.