How system takes promise date for planned production orders in MRP Detail Inquiry. 

I would like to know in three different constraint

  1. Finishes on
  2. Starts on
  3. User Entry 

We take for an assumption 6 working days as manufacturing lead time. How system takes promise date for all the three scenarios. 

icon

Best answer by Debbie Baldwin 31 July 2023, 15:19

View original

1 reply

Userlevel 7
Badge +2

@balajid30  - Hi there - I found this in the Help. 

 

Reply


About Acumatica ERP system
Acumatica Cloud ERP provides the best business management solution for transforming your company to thrive in the new digital economy. Built on a future-proof platform with open architecture for rapid integrations, scalability, and ease of use, Acumatica delivers unparalleled value to small and midmarket organizations. Connected Business. Delivered.