MRP

  • July 31, 2023
  • 1 reply
  • 58 views

How system takes promise date for planned production orders in MRP Detail Inquiry. 

I would like to know in three different constraint

  1. Finishes on
  2. Starts on
  3. User Entry 

We take for an assumption 6 working days as manufacturing lead time. How system takes promise date for all the three scenarios. 

Best answer by Debbie Baldwin

@balajid30  - Hi there - I found this in the Help. 

 

1 reply

Debbie Baldwin
Acumatica Moderator
Forum|alt.badge.img+2
  • Acumatica Product Manager
  • Answer
  • July 31, 2023

@balajid30  - Hi there - I found this in the Help.