Skip to main content
Answer

Labor in Production Orders for BOMs with Phantom Items

  • September 5, 2025
  • 1 reply
  • 52 views

I am trying to see how much labor is required for producing Items but I keep running into issues with how  qty to produce for each operation ID is calculated.

From what I have seen it is setting it to be always equal to the qty of the Inventory ID you are trying to make. 

Shouldn’t it be equal the the quantity needed in the BOM times the qty of the inventory ID?

The materials seem to get calculated correctly and lists the total qty of the subparts under each operation ID correctly.

 

Anyone else run into this?

I have attached an example Production order with the first step being one that should have made a qty of 3. 

 

Best answer by angierowley75

This fix will be available in the 2026R1 release.

1 reply

angierowley75
Acumatica Moderator
Forum|alt.badge.img+3
  • Acumatica Moderator
  • Answer
  • September 5, 2025

This fix will be available in the 2026R1 release.