Infinite Capacity Production Planning

  • 2 October 2023
  • 1 reply
  • 87 views

Userlevel 1

Hi Everyone,

Is there a way to do infinite capacity production scheduling? It seems like MRP uses infinite capacity, but we’re struggling to see how we would make this work with scheduling production operations.

For example, a client would is wondering if they could have the ability to schedule 10 production orders (work center WC10 and operation 0010) all at the same time block on a given day.

Ie. For all 10 production orders, operation 0010 would start (or be scheduled to start) at 9:00am, all in Work Center WC10

icon

Best answer by angierowley75 2 October 2023, 21:58

View original

1 reply

Userlevel 7
Badge +3

By default the Production Orders are infinitely scheduled.

Just manually set the Start Date (forward scheduling) or End Date (backward scheduling) on the Production Order Maintenance screen and the End Date / Start date calculated will not consider capacity.

Reply


About Acumatica ERP system
Acumatica Cloud ERP provides the best business management solution for transforming your company to thrive in the new digital economy. Built on a future-proof platform with open architecture for rapid integrations, scalability, and ease of use, Acumatica delivers unparalleled value to small and midmarket organizations. Connected Business. Delivered.