We are very new to Acumatica. We have monthly consolidated scheduled ocean shipments. Most of my ‘DEFER” on the exception list is due to we put in on the earlier ocean to arrive in time. For instance, I have a 6/25/25 scheduled ocean, and MRP is telling me to DEF to 7/9/25. I don’t have a 7/9/25 ocean, and need to make sure it’s on the 6/25/25 ocean. Is there any schedule we can put in for our ocean, or once it moves to “IT-OCEAN-MTL” warehouse, it won’t show to defer or expedite since it’s not possible for either.