The customer is using Multi-Level BOM with Phantom Parts. Cost Rollup is a bit inconsistent. 

for some subassemblies it’s adding up the cost to Parent Part, for others it's not incorporating. 

Any pointers?

 

 

Best answer by angierowley75

It looks like you are on a later build than where the issue was found/fixed.  I do not know the process for how an OEM like MYOB logs issues - but I would recommend this be logged for further research.  It would be good to have access to the data in order to research and assist.

3 replies

angierowley75
Acumatica Moderator
Forum|alt.badge.img+3
  • Acumatica Moderator
  • December 5, 2022

What version are you running - there is a known issue (resolved) for Multi-level BOM cost calculation in 2021R1 and 2021R2


  • Author
  • Freshman I
  • December 5, 2022

Build 2021.213.204.9588 [21.213.0038] Customization: ExobizBase202011131,SalesOrderExtPrice,AXSCS101500ExtraFields,IIGRentalProcessing2021.213.204R04
Base template: AUSTRALIA
Product Edition: Manufacturing

 

I am new to Acumatica, Worked on various other ERPs in Mfg Domain. just learning.

if it's a known issue with this product, customer need to log a support ticket?

Thanks again for your help


angierowley75
Acumatica Moderator
Forum|alt.badge.img+3
  • Acumatica Moderator
  • Answer
  • December 5, 2022

It looks like you are on a later build than where the issue was found/fixed.  I do not know the process for how an OEM like MYOB logs issues - but I would recommend this be logged for further research.  It would be good to have access to the data in order to research and assist.