Skip to main content
Answer

Importing BOM Attributes - Associating BOM values correctly

  • March 13, 2024
  • 1 reply
  • 111 views

Forum|alt.badge.img

Trying to import 8 attributes and corresponding values to the BOM but the import is mixing up the values and associating them incorrectly.

Import Scenario

Data / Import By Scenario

Results

As you can see the values are not being applied to the correct Attribute. How should I be adjusting my import scenario?

Best answer by CNeels

Hi @jwarren 

 

I would recommend trying out turning on the “Commit” action in the Import Scenario for the Value lines and/or the <Line Number> lines. 
 

This could help with the values being assigned in the correct order/ to the correct field. 

1 reply

  • Freshman II
  • Answer
  • May 2, 2024

Hi @jwarren 

 

I would recommend trying out turning on the “Commit” action in the Import Scenario for the Value lines and/or the <Line Number> lines. 
 

This could help with the values being assigned in the correct order/ to the correct field.