Skip to main content
Solved

Change Order Not Showing on WIP Report

  • February 24, 2025
  • 1 reply
  • 53 views

Hi! Would anyone know why a CO that was recorded/approved in the correct month would not show on the Project WIP with date range report for that timeframe? The task, CO, and approval of said CO was entered December 2024. Another was entered Jan 2025 but both only show in January and nothing in December. Thanks!

Best answer by hdussa

Hello ​@SarLovell23 ,

 

I remember the project WIP report will display only the projects that have a start date earlier than or within the specified fin. period defined in the master fin. calendar. I would check whether the dates matching the fin. period.

 

Hope this helps!

1 reply

hdussa
Jr Varsity I
Forum|alt.badge.img+2
  • Jr Varsity I
  • Answer
  • February 25, 2025

Hello ​@SarLovell23 ,

 

I remember the project WIP report will display only the projects that have a start date earlier than or within the specified fin. period defined in the master fin. calendar. I would check whether the dates matching the fin. period.

 

Hope this helps!