PO changes allowed for lock commitment projects

  • December 19, 2025
  • 1 reply
  • 13 views

Hi All,
I have created a Project and a PO against the project when the commitments are allowed to the Project.

 

When i lock commitments to this project and go back to the PO, put the PO on hold and add new lines to this, the system is allowing me to change it instead of restricting it.

 

 

 

 

 

Related source

 

Am i missing any steps here?

1 reply

Heidi Dempsey
Community Manager
Forum|alt.badge.img+3
  • Community Manager
  • December 19, 2025

@yasalimadihahewage I just tested this in 25R2 and notice the same behavior.  Please enter a case so we can escalate this.  Thank you.