One specific cost code shows actual quantity of 58. However all transactions (hours) posted to that code should be over 300. Any idea why this is reporting incorrectly?

  • July 17, 2023
  • 7 replies
  • 163 views
  • Translate All

Forum|alt.badge.img

we have a job setup with a cost code of 01-0500 Labor. When I view this cost code from Projects > Cost Budget it shows Actual Quantity of 58. However the actual amount is well beyond what 58 x our hourly rate would be.

If I export all the time entry / payroll transactions that have hit that cost code, they are truly 315.5. And if I divide the ACTUAL AMOUNT / 315.5 that is accurate and correct.

So my question is any idea why the cost budget would be showing only 58 hours?

 

Best answer by iqraharrison

@brandontfrank have you tried to recalculate the project balance?

 

View original

7 replies

Heidi Dempsey
Community Manager
Forum|alt.badge.img+3

@brandontfrank  Thanks for the question.  Is it just the quantity not reporting accurately?  Check the UOM on the transaction and the budget.  Do they match?  They probably do not so open Unit of Measure Screen [CS203100] and make a conversion for the UOM on the transaction to the UOM on the budget.  You can then recalculate balances and the quantity should update accordingly.  Hope this helps.

Translate

iqraharrison
Captain II
Forum|alt.badge.img+9

@brandontfrank i had this issue before and found that the UOM was either not entered or didn’t match.  in order for the system to accurate show the quantity, the UOM must match (or have the conversion as heidi stated).

 

Translate

Forum|alt.badge.img

@Heidi Dempsey @iqraharrison48  I checked that and the Project Transaction Detail for that code shows HR for all UOM. 

Translate

iqraharrison
Captain II
Forum|alt.badge.img+9

@brandontfrank have you tried to recalculate the project balance?

 

Translate

Laura03
Captain II
Forum|alt.badge.img+20
  • Captain II
  • July 31, 2023

Hello, @brandontfrank ,

Did any of the Project’s transactions post to Cost Code 01-0500 and post to a different Account Group, or to a different GL account that is not connected to Account Group L?

Laura

Translate

Heidi Dempsey
Community Manager
Forum|alt.badge.img+3

@brandontfrank  If  the project transactions all have HR for UOM and the Budget shows HR for UOM, and you have recalculated Project Balances and the quantity is still incorrect, please enter a case and let me know the case number so I can check on it.

Translate

Forum|alt.badge.img

@brandontfrank have you tried to recalculate the project balance?

 

@iqraharrison48 thank you - this fixed the issue. I wasn’t aware of the recalculate option!