Skip to main content
Solved

Change request description isn't carried over when clicking on the Create Change Order from the change request

  • February 20, 2026
  • 5 replies
  • 117 views
  • Translate All

We are almost ready for Go-live and the customer noticed that the description from the change request isn’t carried over to the Change Order.

 

The process:

  1. Change request creation 00001
  2. Click on the Create Change Order button to create the Change Order 
  3. While looking at the cost budget it’s empty.

 

As seen on the screenshot below:

 

Best answer by haarshita51

​@malcom , You can import the descriptions for the lines or add any new via import scenarios in Projects (PM301000) screen.
FYI, Your change request & order creation steps are perfect.

View original

5 replies

Forum|alt.badge.img+4

hi ​@malcom ,

Can you confirm if the descriptions have been defined under the Cost Budget Tab → Projects (PM301000) screen?

Hope this Helps!!

Translate

  • Author
  • Freshman I
  • February 20, 2026

​@harshitasethia74  Good question and they were not defined because they are not part of the initial contract so they should add the new lines in the Project budget lines. Is it possible or we must absolutely create the lines in the project budget before doing the change ? That will take a lot of time.

Translate

Forum|alt.badge.img+4
  • Varsity III
  • Answer
  • February 20, 2026

​@malcom , You can import the descriptions for the lines or add any new via import scenarios in Projects (PM301000) screen.
FYI, Your change request & order creation steps are perfect.

Translate

MShields61
Jr Varsity III
Forum|alt.badge.img
  • Jr Varsity III
  • April 2, 2026

That is a duplication of efforts, I agree that will take a lot of additional time.  The information is entered to the request and then has to be manually replicated in the project Cost Budget, even if the COR will never be approved.

Translate

Janella
Varsity I
Forum|alt.badge.img+1
  • Varsity I
  • August 14, 2026

I’d call this Partially Solved. Importing afterward is still a second step. Ideally, the Change Order description line should carry through from Change Request to Change Order and From the Change Order to the Revenue Budget, so it can flow directly to the invoice/AIA without additional entry.

Translate