Hello everyone, so one of my client agree to update their Acumatica Version from 24R2 to version 25R2, but we were still on progress to update the environment (not yet go-live), is that possible to doing the upgrade?
Please lemme know about the procedure of this, I really appreciate thank you.
Solved
Update Version Acumatica 25R2
Best answer by Naveen Boga
Here’s the recommended approach and procedure.
- Take full database and customization backups
- Clone the existing 24R2 environment
- Install Acumatica ERP 25R2 on the cloned environment
- Point the new site to the copied database
- Run the database upgrade
- Publish all customization packages
- Fix any compilation/customization issues
- Validate integrations, reports, workflows, and APIs
- Perform UAT testing
- Take backup of the actual 24R2 environment
- Upgrade the actual environment to 25R2
- Publish validated customizations
- Perform smoke testing
- Continue implementation and go live on 25R2
Important Tips
- Do not skip the TEST upgrade, even on a non-production environment
- Check Acumatica's Release Notes for both 25R1 and 25R2 since you're jumping two versions — breaking changes in 25R1 also apply to you
- Engage Acumatica Support if you hit database upgrade errors — do not try to manually fix schema issues
- Since you mentioned customizations (we can see several active in your trace logs) budget extra time for recompiling and testing each one