Hi everyone,
One of our clients upgraded within our implementation process to 2022R2.
They will be a heavy user of the Manufacturing suite.
We imported some sample Bill of Materials for Training purposes and realized that the Order on the Visual BOM follows some other logic than the Engineering Workbench.
The Engineering Workbench shows the 1:1 replica of the BOM in terms of Operations and Materials.
The Visual BOM seems to take the BOM ID from the nested BOM into consideration. It mixes the order of Materials up completely. Is anybody aware of the Logic behind it?
The User is trained to consider the order of Materials when creating the BOM. It is easy to change through the Engineering Workbench, but once again the Visual BOM seems to have a different Ordering Sequence for that.
Did anybody experience similar things before or knows why the two screens use different Ordering sequences?