Unable to create demand through mps and forecast

  • March 6, 2024
  • 6 replies
  • 198 views

Forum|alt.badge.img

Hello experts, I am facing issue while generating demands from MPS and forecast, for Eg. :- I have created a demand from so for date 06/03/2024 for item A and run the MRP demand from sales order gets reflected but when I am creating demand on MPS for item ‘B’ and a forecast for item ‘C’ of same date as on sales order my MPS and Forecast demand are not getting into MRP display screen and in MPS screen active check box goes inactive.  

Best answer by Debbie Baldwin

@vishalsharma49 - check  your demand time fences….

 

6 replies

Debbie Baldwin
Acumatica Moderator
Forum|alt.badge.img+2
  • Acumatica Product Manager
  • Answer
  • March 6, 2024

@vishalsharma49 - check  your demand time fences….

 


Forum|alt.badge.img

hi Debbie, time fence for forecast aswell as mps its already set to 30


Debbie Baldwin
Acumatica Moderator
Forum|alt.badge.img+2
  • Acumatica Product Manager
  • March 7, 2024

@vishalsharma49 - can you please attach a screenshot of your MRP parameters? Also your forecast and MPS screen. Have you played around with your quantity on Forecast? (to make sure your sales orders are not consuming your Forecast?) We will know more once we see the screenshots. 


Forum|alt.badge.img

 

Hello Debbie, here is the screen shot for two demands one from sales order and one from master production schedule.

 

after running mrp only demands comming from sales order is displayed in mrp screen, but demand from master production schedule is not reflected to inventory planning display screen of same date which is on sales order


Forum|alt.badge.img

 


Debbie Baldwin
Acumatica Moderator
Forum|alt.badge.img+2
  • Acumatica Product Manager
  • March 20, 2024

@vishalsharma49 - were you able to figure this one out?