Has anyone else been experiencing significant issues with MRP in 24R2 (particularly 24.211.0024)?
- Could not create production orders from MRP - fixed by upgrading to 24.211.0024
- MRP recommending incorrect action dates - fixed with hotfix
- Overhead calculations incorrect causing a workaround to be applied - unsolved, waiting on Acumatica RnD team (not MRP related but thought I’d mention this also)
- MRP recommending too many orders due to the system subtracting (1) from every existing order already on the floor (basically, the system does not even see an open order for qty 1 of a part, if qty is 2 it only sees 1) - unsolved, waiting on Acumatica RnD team
This last one has potential to cause significant disruptions for our business due to MRP recommending too many orders, causing confused priorities on the shop floor and creating false late orders.