reschedule production tickets?

  • 30 October 2021
  • 4 replies
  • 49 views

Userlevel 1
Badge

After releasing a pile of production tickets the sales order due date has been pushed out over a month and now I want to update all those tickets (reschedule them).  Is this possible? 

icon

Best answer by angierowley75 1 November 2021, 13:16

View original

4 replies

Userlevel 5
Badge +2

To edit the Production Order business document, you can put it on hold, make a change (like the Constraint Date), and then remove the hold.

If you have APS, you can re-schedule on the Rough Cut Planning screen.  

Userlevel 1
Badge

Hello and thank you for the reply.  There are approx 60 associated with this one order alone.  Doing one by one is quite cumbersome. 

Userlevel 5
Badge +2

It is probably possible to write a customization which will do a mass update - but there is no standard tool in the core MFG module.

Userlevel 1
Badge

Thanks we are exploring the possibility of mass deleting and re-creating them.  

Reply


About Acumatica ERP system
Acumatica Cloud ERP provides the best business management solution for transforming your company to thrive in the new digital economy. Built on a future-proof platform with open architecture for rapid integrations, scalability, and ease of use, Acumatica delivers unparalleled value to small and midmarket organizations. Connected Business. Delivered.