Production Substitution.

  • Dec 11, 2023 2:31 PM UTC
  • 4 replies
  • 484 views
  • Translate All

Does Acumatica have any option to substitute the Component material in production?

Best answer by jharris

Does Acumatica have any option to substitute the Component material in production?

Not really in production, but you can do this by using alternate BOM’s with different components before sending to production.  These alternate BOM’s can be for the same finished goods or components.  You just need to select which BOM you want to use before creating the production order and it will consume the materials desired.

This is the current workaround until Acumatica accepts our request for the alternate parts in a BOM idea…  But it’s been 3 years so far…  Not holding our breath haha…  There’s always next year ;) 
https://community.acumatica.com/ideas/allow%2Dalternate%2Did%2Dparts%2Don%2Dbom%2D883

 

 

View original

4 replies

angierowley75
Acumatica Moderator
Forum|alt.badge.img+3
  • Acumatica Moderator
  • Dec 11, 2023 4:53 PM UTC

If I am understanding your question correctly - I believe there is a product enhancement idea for the feature you need:

 

Translate

  • Author
  • Freshman I
  • Dec 11, 2023 9:13 PM UTC

@angierowley75 Thanks for the reply. I’m just trying to understand do we have any option to substitute the component material in the production order or BOM like we are doing in the sales order substitution. Just for one BOM or Production order directly in that without any mass processing.

 

Translate

Forum|alt.badge.img
  • Semi-Pro II
  • Jan 11, 2024 12:48 AM UTC

AFAIK manually is the only way. Delete and add a new material in your Production Order Details screen. If the order already has material issued, mark your old material as 0 quantity instead of deleting.

Translate

jharris
Semi-Pro I
Forum|alt.badge.img+8
  • Semi-Pro I
  • Answer
  • Feb 8, 2024 11:05 PM UTC

Does Acumatica have any option to substitute the Component material in production?

Not really in production, but you can do this by using alternate BOM’s with different components before sending to production.  These alternate BOM’s can be for the same finished goods or components.  You just need to select which BOM you want to use before creating the production order and it will consume the materials desired.

This is the current workaround until Acumatica accepts our request for the alternate parts in a BOM idea…  But it’s been 3 years so far…  Not holding our breath haha…  There’s always next year ;) 
https://community.acumatica.com/ideas/allow%2Dalternate%2Did%2Dparts%2Don%2Dbom%2D883

 

 