Outside Processing Production Order not Receiving Purchase Receipt QTY?

  • Nov 18, 2025 9:38 PM UTC
  • 3 replies
  • 87 views
  • Translate All

Forum|alt.badge.img

I’ve got a Outside Processing Production Order that uses Purchase Orders to complete one of the steps, however, upon release of the Purchase Receipt, nothing happens. All of them are linked together, however, the qty on the specific line in the production order is unfulfilled. Is there a specific step that I missed that would be causing this issue.

The Production Order’s Link to the PO
The Purchase Order
Purchase Receipt
Production Order Line still unfufilled.

 

Best answer by dgodsill97

Unless you are on 24R2 or later you have to use the Unreleased Material Allocations to issue the stock items to the production order.  

View original

3 replies

Forum|alt.badge.img+5

​@kkraus Can you check if subcontract Source is defined.

Translate

Forum|alt.badge.img
  • Author
  • Freshman II
  • Nov 19, 2025 6:57 PM UTC

​@kkraus Can you check if subcontract Source is defined.

​@ranjithduraisamy72 yep, it is.

 

Translate

dgodsill97
Varsity I
Forum|alt.badge.img+6
  • Varsity I
  • Answer
  • Nov 19, 2025 9:35 PM UTC

Unless you are on 24R2 or later you have to use the Unreleased Material Allocations to issue the stock items to the production order.  