Skip to main content

I did Multi Level Cost roll for Sub assembly Item and then on the finished goods , however it shows VOH and VL on Subassembly item not on Finished goods   , Kindly advise

Can you add more detail? perhaps screen shots?  are you expecting the cost of the subassembly to be broken out on the finished good?  


 

ID59018 is FG with 11031 is subassembly part has a cost … this cost need to be rolled up to the 59018 FG /BOM  total Cost .  However this is showing when we run Multi level BOM Cost 

 


@jvarughese23

The multi level BOM report will show you how the totals are calculated and break out the cost components on the report.

 

The subassembly costs on cost roll are factored into the material cost for the finished good. When a production order is created the subassembly costs are included as material costs. The cost roll most closely resembles what the production cost will look like.


@andrestamour43 .. I tried to create a GI  in TST Revision Two  Product DB and after doing the MultiCost roll it shows VOH and VL on Finished Goods  which has Sub assembly Items used BOM1 and BOM 4 .   

 


Hi @jvarughese23 were you able to find a solution? Thank you!


@Chris Hackett No Solutions yet