Hi All,

Is there a way to issue a material to a production order other than a material that has been specified in the BOM?

Thank you!

1 reply

Forum|alt.badge.img
  • Semi-Pro II
  • August 10, 2022

You should be able to manually issue selected materials to a production order using the Materials screen.

 

If you are not able to, try checking under Production Order Types to see if ‘Issue Material not on Order’ is allowed.