say bomA using RM A in op10, last cost for A is 6.00
10 days later, new po cost for A is 7.00.
how can i update bomA to reflect RM A to 7?
thank you
Zoey
say bomA using RM A in op10, last cost for A is 6.00
10 days later, new po cost for A is 7.00.
how can i update bomA to reflect RM A to 7?
thank you
Zoey
In the Bill of Material Workspace there is a Cost Roll (AM508000) Process that will perform this function. Read through the on-line help file of this screen for guidance. I will try to answer more specific questions if you have them.
thank you! problem solved.