A client has the following requirements:
- All work centers have finite capacity except the Drying process
- the drying process can continue all day without any restrictions to how much product can be dried in a day
I have tested Finish Time, Move Time and Queue time - but these times only consume from the available capacity of the work center.
I have read the Wik and whitepaper on APS, but not quiet sure how to setup for this requirement.
Anyone has a similar process working?