Hello,
Sometimes operations are completed out of order on a production order. Assuming the production order’s operations are numbered 10, 20, 30, etc…. I give the following example.
If I say I completed operation 40, Acumatica then marks operation 10,20 and 30 as completed as well. It does this even if they are not marked as backflushed.
If I make operation 30 a control point, I will get an error when I try to report a completion on 40.
However, I legitimately want to report a completion on 40. And not have operations 10, 20 or 30 record the completion since I just did operation 40 only.
There is no way in Acumatica to report against operations out of order is there?
Thanks!
Larry
Best answer by angierowley75