Hello all,
I want to know if tyats a possibility to create inter-unit production processes have 2 sites in Acumatica? Can anyone guide me thru this.
Thanks
Hello all,
I want to know if tyats a possibility to create inter-unit production processes have 2 sites in Acumatica? Can anyone guide me thru this.
Thanks
Best answer by josborn02
I don’t believe it can be done within the same production order or BOM. I’d suggest creating two phantom subassemblies, one for each site. The first operation in site 2 has subassembly 1 (from site 1) on the BOM, then the rest of the operations occur in site 2. As long as the inventory planning settings are correct for both subassemblies (Item Warehouse Detail screen), it should work!