Explanation of Queue, Finish, Move Times in Routings

  • May 4, 2026
  • 5 replies
  • 70 views

Forum|alt.badge.img+1

Wanted to share this with the community!  I think the visual helps a person understand Queue, Finish, and Move Times more quickly.

5 replies

dgodsill97
Varsity I
Forum|alt.badge.img+6
  • Varsity I
  • May 5, 2026

These times are used in scheduling but they are not used for costing an operation.


Forum|alt.badge.img+1
  • Author
  • Varsity I
  • May 5, 2026

Correct, thank you for clarifying that, ​@dgodsill97!


Chris Hackett
Community Manager
Forum|alt.badge.img
  • Acumatica Community Manager
  • May 5, 2026

Thank you for sharing this with the community ​@danielklumpp!


angierowley75
Acumatica Moderator
Forum|alt.badge.img+3
  • Acumatica Moderator
  • May 12, 2026

We/Acumatica generally say that the Use Case for finish time is for drying or curing - when a production item needs to occupy the WC - consuming capacity - even though the work done in that WC is complete. 

And another Use Case for move time is when the production item needs to physically move from one building to another before the next step in the operation can be started.  The move time does not consume capacity.


jdobish
Pro III
Forum|alt.badge.img+2
  • Pro III
  • May 19, 2026

it would be nice if we could use different time fences in the queue or move time. For example, it might take 3 minutes to paint, but needs to cure for 48 hours.