Explanation of Queue, Finish, Move Times in Routings

  • May 4, 2026 9:01 PM UTC
  • 5 replies
  • 124 views
  • Translate All

Forum|alt.badge.img+2

Wanted to share this with the community!  I think the visual helps a person understand Queue, Finish, and Move Times more quickly.

5 replies

dgodsill97
Varsity I
Forum|alt.badge.img+6
  • Varsity I
  • May 5, 2026 3:41 PM UTC

These times are used in scheduling but they are not used for costing an operation.

Translate

Forum|alt.badge.img+2
  • Author
  • Semi-Pro I
  • May 5, 2026 4:07 PM UTC

Correct, thank you for clarifying that, ​@dgodsill97!

Translate

Chris Hackett
Community Manager
Forum|alt.badge.img
  • Acumatica Community Manager
  • May 5, 2026 9:23 PM UTC

Thank you for sharing this with the community ​@danielklumpp!

Translate

angierowley75
Acumatica Moderator
Forum|alt.badge.img+3
  • Acumatica Moderator
  • May 12, 2026 1:32 PM UTC

We/Acumatica generally say that the Use Case for finish time is for drying or curing - when a production item needs to occupy the WC - consuming capacity - even though the work done in that WC is complete. 

And another Use Case for move time is when the production item needs to physically move from one building to another before the next step in the operation can be started.  The move time does not consume capacity.

Translate

jdobish
Captain II
Forum|alt.badge.img+2
  • Captain II
  • May 19, 2026 7:02 PM UTC

it would be nice if we could use different time fences in the queue or move time. For example, it might take 3 minutes to paint, but needs to cure for 48 hours. 

Translate