Different Planning Methods per warehouse

  • 8 February 2024
  • 2 replies
  • 88 views

We use the MRP Planning method for one of our warehouses but Inventory Planning for our replenishment from the suppliers. 

We used to be able to do this in the older versions but with 23R2 they have taken to function away. 

Does anyone know how I might be able to get around this? 

Here is the use case:

One of our warehouses is the aftermarket warehouse. This warehouse does not replenish from the supplier unless our OEM warehouses does not carry the item sold. 

In most cases they are transferring items from the other warehouses to it using the MRP Display (Now Inventory Planning Display). 

With 23R2 you have to choose one inventory planning method for an item, and at our OEM warehouses we want to use the Inventory Planning method, but when you do that, those items fall off the MRP Display. 

2 replies

Userlevel 7
Badge +2

@bradmestach - we have identified this as an issue and will be making a fix that allows you to select the Planning Method by Item warehouse (not just by item). Please enter a support case so that you can be notified when this will be available. 

Userlevel 5
Badge +1

@Debbie Baldwin I’m glad this is getting addressed. I have had some big hurdles to go through to try and get these numbers to be fixed. Please keep us posted when this is done (i have a support case open already) as a lot of our customers would love to get back to using Min/Max methods for transfers, but safety stock / reorder point for manufactured items. 