We have a client using configurator for make to order items. Production Orders are linked to Sales Order lines. But when MRP runs, it doesn’t seem to recognize these links. MRP is allocating any current as yet unshipped and differently configured inventory to satisfy the next-to-ship sales orders, even though those orders are linked to existing open production orders.
Does anyone have ideas on how to get MRP to use the linked production orders instead?
Best answer by dsimone20
View original