Best Practice for Capturing Actual Machine Running Hours and Calculating Production Costs in Acumatica Manufacturing

  • Nov 17, 2026 11:38 AM UTC
  • 1 reply
  • 28 views
  • Translate All

RuwanK
Freshman I

Hello Acumatica Community,

We are a glove manufacturing company using Acumatica Manufacturing Edition across multiple factories.

Our production process includes three BOM levels:

  1. Compound BOM

  2. Catalog Product BOM

  3. Finished Goods (FG) BOM

Current Issue:

Our production costing is based on standard/pre-allocated machine hours and overhead costs. We have not identified a facility to capture actual machine running hours against production orders.

This impacts production cost accuracy, overhead allocation, machine efficiency analysis, and cost variance reporting.

We would appreciate your guidance on:

  1. Does Acumatica support capturing actual machine running hours against production orders?

  2. Can actual machine hours be used for production costing and overhead allocation?

  3. What is the best practice for actual costing across multiple BOM levels?

  4. Can this be achieved through standard Acumatica functionality, or is customization required?

We appreciate your recommendations and experience with similar manufacturing environments.

Best Regards,
Ruwan Kumara
Lalan Group

1 reply

dgodsill97
Varsity II
Forum|alt.badge.img+6
  • Varsity II
  • Nov 17, 2026 3:57 PM UTC
  1. no, it only captures the machine cost when a Move/Labor transaction reports a qty
  2. no, the cost is backflushed only
  3. Costs from lower levels are folded into the material cost so you cannot break down the costs by cost element,  If the production orders are linked, e.g., the Product Production order is on the references tab,you could create a GI to sum up the costs by cost element.
  4. customization maybe,  look at https://www.smartfactorymom.com/ or https://lynqmes.com/ if you are interested in data collection from machines.