We have a few blends of product that need to sit in the tank overnight to finish processing. Our shift is M-TH 6:00am - 4:30pm. The tank (machine) shows the same schedule, but we have machine time on the BOM as 16 hours. The APS module is scheduling it over 2 - 3 days depending on the start time. Our employees do not need to be present for the processing to take place once ingredients are placed in the tank. If I change the machine shift to 24/7, it still will not calculate appropriately. If I change the work center to have the 24/7 shift, it schedules around the clock. I have tried to use queue time and finish time as well, but they are not yielding appropriate results either. Essentially, I need 1-2 hours of shift time and the remaining is processing time overnight, then the tank can be emptied the following morning, cleaned and reused. Is it possible to replicate this scenario on a BOM & in the APS module?
APS machine time vs shift
Best answer by ChrisOkamuro52
Unfortunately, we don’t have the ability to designate a portion of the setup or runtime of a work center as being unattended. We do have items in the future plan that can address this.
As for what you can do in the existing system, you have a couple options, but I regard this as the “best”:
You can alter the shift calendar efficiency to account for the difference in clock and shift time. The straight math for this would be 24/10.5, but you can roughly adjust this to account for the general ratio of attended to unattended time. This isn’t a perfect solution, but it does keep the inter-operation transfer times within the proper time aperture.
We’re currently working on enhancements to APS that will better model scenarios like this.