Hello,

We are working on some cleanup work on old projects and need to change the status of jobs from Completed to Active. I wanted to do a import scenario since we have about 500 jobs we are touching. 

I keep receiving a error on the import, couple screenshots below.

1: Error message:

2: Import scenario build:

Thank you,

Kage

Best answer by Laura03

Hello,

Please try to activate the projects using Activate action, as shown in this example (Acumatica version 2024 R1).

Laura

2 replies

Laura03
Captain II
Forum|alt.badge.img+19
  • Captain II
  • Answer
  • June 5, 2024

Hello,

Please try to activate the projects using Activate action, as shown in this example (Acumatica version 2024 R1).

Laura


ketiller
Jr Varsity III
Forum|alt.badge.img
  • Author
  • Jr Varsity III
  • June 5, 2024

@Laura02 That worked! thank you!