Subaccount Mask for Project/Project Task unavailable under Reason Codes for Issue of Stock for Projects

  • April 7, 2025
  • 2 replies
  • 96 views

Hi everyone. I am hoping that someone can help me find the cause of my issue.

I am trying to setup reason code, so when an inventory item is issued to project task, it uses the subaccounts from default cost subaccount of the project task. 

I am following this documentation below. but so far unsuccessfully. When I set combine Sub From box to TTTTTT, it says “TTTTTT does not exist in the system”. Subaccount segment key is set to 6 characters. 

Could someone please point me to the right direction?

Much appreciated.

Best Regards

Best answer by valentynbeznosiuk

Good day,

 

What Acumatica build are you using right now? These options become available with the 24R2 release. You can find more information in the Release Notes, p. 143

2 replies

valentynbeznosiuk
Jr Varsity I
Forum|alt.badge.img+3

Good day,

 

What Acumatica build are you using right now? These options become available with the 24R2 release. You can find more information in the Release Notes, p. 143


  • Author
  • Freshman I
  • April 10, 2025

Good day,

 

What Acumatica build are you using right now? These options become available with the 24R2 release. You can find more information in the Release Notes, p. 143

Thank you. Our site has not been updated yet. That explains it. 

Much appreciated.