Can I edit a PO with an existing prepayment?

  • November 7, 2024
  • 6 replies
  • 150 views

Forum|alt.badge.img

When I have an open purchase order that has an existing prepayment applied, I am not able to cancel any line on the purchase order. Even if I void the prepayment check, which also voids the prepayment request, I am not able to modify the PO. I receive the following error. The only solution I have found is to void the prepayment and cancel the entire PO for re-entry, which is not ideal. Any other suggestions?

 

PO Error: The line cannot be deleted because one or multiple prepayment requests have been generated for this order. To proceed, delete prepayment requests first.

Best answer by rkenna

Hi ​@kristybrooks83 

 

There is no way to edit it. What I would recommend is to mark the specific line as Complete and Cancelled (the checkbox on the line itself). This way, it does not require you to receive those items.

6 replies

debbiereed72
Varsity I
Forum|alt.badge.img
  • Varsity I
  • November 27, 2024

@kristybrooks83  Did you get an answer for this?

We also have this same issue/problem with a client.  Since the prepayment was not yet paid, we just voided the released prepayment; but still cannot modify lines on the PO.


Chris Hackett
Community Manager
Forum|alt.badge.img
  • Acumatica Community Manager
  • January 23, 2025

Hi ​@kristybrooks83 were you able to find a solution? Thank you!


Manikanta Dhulipudi
Captain II
Forum|alt.badge.img+15

@kristybrooks83  Did you get an answer for this?

We also have this same issue/problem with a client.  Since the prepayment was not yet paid, we just voided the released prepayment; but still cannot modify lines on the PO.

@debbiereed72 I am able to edit the qty when the Prepayment is attached.


Forum|alt.badge.img
  • Author
  • Jr Varsity II
  • August 5, 2025

@Chris Hackett I do not have a resolution for this yet.


Forum|alt.badge.img
  • Captain I
  • Answer
  • August 5, 2025

Hi ​@kristybrooks83 

 

There is no way to edit it. What I would recommend is to mark the specific line as Complete and Cancelled (the checkbox on the line itself). This way, it does not require you to receive those items.


Forum|alt.badge.img+2
  • Captain II
  • August 5, 2025

Please feel free to add more suggestions to this idea

https://community.acumatica.com/ideas/po%2Ddeposits%2D31007

 

I think many of us are looking for a much more flexible/simple system for allocating prepayments to POs in the same way AR-prepayments can be allocated to a sales order