I’ve read through the instructions on how to Link a Line on a AP Bill to a Landed Cost document, however I can’t seem to get it to work once the bill is released. 

Is that a known limitation? It’s not noted on the Wiki help page. 

Best answer by Hannah Barnes

Hi @Jeff96 

If a Bill has already been released, then lines cannot be added unless the user reverses the bill and creates a new one.
For this reason, an Open Bill cannot be linked to a Landed Cost document.

I hope this helps!