Hi,
There is a customer requirement (Construction project) to restrict creating purchase requestions if the budgeted quantity exceeds.
As an example , a budget of 10,000 cement bags has been allocated for a specific construction project. The project execution team has been utilized 10,000 allocated cement bags and the team try to create a new purchase requestion to buy more 100 cement bags.
In this case system needs to restrict creating a new PR since the budgeted 10,000 units of cement bags exceeds by this PR.
Appreciate help on this matter.
Thanks,
Dulanjana
Best answer by vkumar
View original