How is everyone monitoring project inventory costs through their balances/cost budgets? Our issue is that the cost of inventory when ordered will appear on a Committed or Open committed column, but once that project inventory is received (or transferred directly) onto the project, it does not appear in the balances UNTIL those inventory items are issued.
We need a way to reflect project inventory balances on the Balances tab, ideally on the Actual + Open Committed amount column.
Example below. You will see we ordered $303k worth of inventory. It is all received and sitting on the project inventory. But it is not reflected in the Actual +Open Committed amount and is actually showing as a major variance. Between transfers & PO orders, there is $307k worth of materials sitting on this job that are not being accurately reflected at this WIP state of the project.
How is everyone handling project inventory for budgeting/cost tracking?