Project End Date

  • August 1, 2024
  • 2 replies
  • 105 views

Forum|alt.badge.img

We are running into an issue with the Construction Project End Date due to the fact that we need to make end of year journal entry updates and to do so we must activate the project again. When we mark the project as closed after making our updated journal entries, it is updating the project end date to the current date which cause issues with our Project WIP report. Is it possible to manually set the Project End Date after Completing the project so that are reports remain accurate?

Best answer by Heidi Dempsey

@jsieber  when you are changing the project end date back, change your business date at the top right in Acumatica and it should work for you.

2 replies

Heidi Dempsey
Community Manager
Forum|alt.badge.img+3
  • Community Manager
  • Answer
  • August 1, 2024

@jsieber  when you are changing the project end date back, change your business date at the top right in Acumatica and it should work for you.


Forum|alt.badge.img
  • Author
  • Jr Varsity III
  • August 4, 2024

@Heidi Dempsey thank you, that worked perfectly.