Question

Project cost Movements

  • 6 September 2022
  • 2 replies
  • 67 views

Quest
Freshman I

Is there ‘a movement in saving or <overrun>’ or similar column available for the project cost budget screen?

 

Or a column for Movement in Estimated Final Cost? This would = last cost at completion - cost at completion.

 

Thanks,

 

 

2 replies

Quest
Freshman I
  • Author
  • Freshman I
  • 6 replies
  • September 13, 2022

Assume there isn’t these fields out of box as I looked at the whole list in detail.

 

But would anybody suggest adding these columns into our customers Cost budget area as customisation would be difficult work and hard to support + maintain? 

 

 


joelhoffman
Acumatica Moderator
Forum|alt.badge.img+2
  • Acumatica Moderator
  • 273 replies
  • September 14, 2022

@Quest 

There is a “Variance Amount” field available, but that is a calculation of Revised Budget vs. Actual Costs. 

Depending on how they are entering the Cost to Complete/Cost at Completion/Percent Complete, we do offer a Cost Projection Entry.  That maintains a history of the related projections, and the current projected values are available within the Project/Cost Budget tab.

You can add columns, as mentioned above, but you may also look at a Side Panel within the Project Screen, which would show the overall Cost Projection results for the row highlighted, or if you create a Generic Inquiry with your calculations, that could be put into the Side Panel too.

 


Reply