Hello All,

We have a client migrating from Dynamics SL where they have the option to update the Cost at Completion with every Budget Revision.  They may have multiple Budget revisions on a single day, especially at the end of month.  We would like to recreate this functionality by creating a Cost Projection by Date for every Cost Budget in Acumatica, but are limited due to Acumatica only allowing one cost project for a date.

Is there any plan to allow multiple Cost Projections by Date for a singe date or revise/correct a Cost Projection for a date?  

Or..has anyone found a work around to allow multiple cost projections for a single date?