How do people deal with the “Total Commitments”, “Open Commitments”, & “Cost to Complete” amounts on the Project Cost Report?  They appear to be values as of the report run date rather than as of the period reported.  This means that if you close your accounting period and start reviewing the report and someone on the construction team enters a new change order, all of these numbers change.  It also means that if you rerun a prior period’s report, all of these numbers might change from what you reported to management, quantity surveyors, banks, investors, etc.  

I’m pretty sure the report pulls these amounts from the data behind the project summary screen and I’m not sure how to change the report to build this data as of a reporting period (or what DAC to use).

We take a couple of weeks to close our accounting and get our reports finalized, surely we can’t expect our construction teams to not enter any change orders for two weeks every month.  Not to mention that we can never reproduce our historic reporting.

This must impact the entire industry so I’m hoping this is just a training issue and that I’m doing something wrong.

Best answer by ESTEPALINA

Hello ​@RHarrison

In 25R2, we introduced new reports Project Committed Cost Summary & Details, which are made as generic inquiries and which show date-specific commitment data. The users selects the date and the system shows the open committed, budgeted, etc. through the selected date not including any future transactions.

You can see a demo in the Construction Breakout session of the Launch Event https://www.acumatica.com/2025-r2-virtual-launch/

More info and links 

 

2 replies

ESTEPALINA
Acumatica Moderator
Forum|alt.badge.img+1
  • Acumatica Moderator
  • Answer
  • October 21, 2025

Hello ​@RHarrison

In 25R2, we introduced new reports Project Committed Cost Summary & Details, which are made as generic inquiries and which show date-specific commitment data. The users selects the date and the system shows the open committed, budgeted, etc. through the selected date not including any future transactions.

You can see a demo in the Construction Breakout session of the Launch Event https://www.acumatica.com/2025-r2-virtual-launch/

More info and links 

 


Forum|alt.badge.img
  • Author
  • Freshman II
  • October 28, 2025

I’ll be watching to see how this is delivered.  The linked item is pretty “sale-pitchie” so I’ll have to wait to see details.

Thanks.