Hi,
We have an inherited client that is on 22.214 and needs to go to 24.210. I know there’s not a direct upgrade process and there will be a couple steps in between. I * think * the path is this:
Current Version | Build Update | Intermediate Version | Final Version |
22.214.0019 | 22.223.0007 | 23.120.0004 | 24.210.0019 |
My questions are these:
- Do I create a sandbox for just the 24R2 version, or do we have to test in each?
- Does Acumatica process the upgrade sequentially in one evening, or will the client have to ‘live’ in each progressive version for a particular period of time?
I haven’t processed an upgrade like this and want to be as efficient with the client as possible.
Thanks!