We have 4 branches, each have employees. In many cases, an employee is branch 1 will help out and work on a project that is part of branch 2. When time is imported through employee time activities, that expense is posted to branch 1 (where the employee belongs), however it should hit branch 2 because that is where the expense incurred. How can I change the expense to hit the branch of the project?

Best answer by freboredo

Did you ever get an answer on this or a direct solution from your VAR/Acumatica support? We are having the same issue, and I’ve got to imagine it’s some type of Boolean statement that has to be added to the coding (ie if project = branch 2 then expenses → branch 2 else expenses -> branch 1). 

We had the same issue where employee cost was going to the branch of the employee instead of the branch of the project. Our VAR ended up having to do a customization project in order to accomplish employee timecard cost went to the project branch.

View original
Did this topic help you find an answer to your question?

3 replies

Did you ever get an answer on this or a direct solution from your VAR/Acumatica support? We are having the same issue, and I’ve got to imagine it’s some type of Boolean statement that has to be added to the coding (ie if project = branch 2 then expenses → branch 2 else expenses -> branch 1). 


Forum|alt.badge.img
  • Jr Varsity II
  • 19 replies
  • Answer
  • February 23, 2022

Did you ever get an answer on this or a direct solution from your VAR/Acumatica support? We are having the same issue, and I’ve got to imagine it’s some type of Boolean statement that has to be added to the coding (ie if project = branch 2 then expenses → branch 2 else expenses -> branch 1). 

We had the same issue where employee cost was going to the branch of the employee instead of the branch of the project. Our VAR ended up having to do a customization project in order to accomplish employee timecard cost went to the project branch.


Doug Johnson
Acumatica Moderator
Forum|alt.badge.img+4
  • Acumatica VP, Product Management
  • 588 replies
  • April 10, 2024

Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings